Mumbai: Construction work underway at bullet train project at Vikhroli
Feb 10, 2023
Construction work is underway at the Mumbai-Ahmedabad bullet train project at Vikhroli.
Mumbai-Ahmedabad bullet train project update: All civil contracts awarded
Jul 03, 2024
The Mumbai-Ahmedabad bullet train corridor has been making steady progress since work began in November 2021. The project initially faced delays due to challenges...
Bridge over Kolak river for Mumbai-Ahmedabad Bullet train project completed
Jul 16, 2024
In a key milestone for the Mumbai-Ahmedabad Bullet Train project, the construction of the bridge over the Kolak River in Valsad district, Gujarat, has...
Bridge on Dhadhar River for Mumbai-Ahmedabad bullet train project completed
Jun 22, 2024
The construction of seven river bridges on Par (320 m, Valsad district), Purna (360 m, Navsari district), Mindhola (240 m, Navsari district), Ambika (200...
Japanese Embassy shares first photos of Mumbai-Ahmedabad bullet train project
Dec 19, 2020
New Delhi [India], December 19 : E5 Series Shinkansen, also known as Japan's Bullet Train, will be modified for use as rolling stock of...
300 km of viaducts completed for Mumbai-Ahmedabad bullet train project
May 20, 2025
The adoption of the Full Span Launching Method has significantly accelerated construction, as full-span girder erection is up to ten (10) times faster than...
Maharashtra: Work on Mumbai-Ahmedabad bullet train project in full swing
Jul 05, 2025
L&T, 3 others bid for Mumbai-Ahmedabad bullet train corridor construction
Apr 13, 2023
1389.5 hectare land acquired for Mumbai-Ahmedabad bullet train project: Minister Vaishnaw
Jul 31, 2024
11th river bridge completed for Mumbai-Ahmedabad bullet train project over Kaveri
Sep 05, 2024
Mumbai-Ahmedabad Bullet Train project: Bridge on Vishwamitri River in Vadodara completed
Aug 06, 2025
NHSRCL completes 100pc land acquisition in Gujarat for Mumbai-Ahmedabad High Speed Rail Corridor project